Basic Project Data

Project Name: Delivery of Air Gap Sensors for Condition Monitoring System
Investor: Electric Power Industry of Montenegro, Niksic, Montenegro
Object Name: Perucica HPP
Installed Power/Turbine Type: Total 307MW/Pelton
Object Location: Niksic, Montenegro
Brief Project Description: “Peru?ica” HPP has seven units with Pelton type horizontal turbines. The total installed power of the power plant is 307MW. The project was implemented as part of the procurement of spare parts (Air Gap Sensors by MC-monitoring) for the existing monitoring systems in “Peru?ica” HPP. The project is realized jointly by IMP Automatika Ltd,Serbia, NORTH Protection Ltd, Member of the NORTH Group, Serbia and EFusion Ltd, Montenegro.